ISLAMABAD: The National Electric Power Regulatory Authority (NEPRA) has reportedly rejected a request by 1,320MW Port Qasim Electric Power Company Limited (PQEPCL) for an extension in coal procurement under an interim arrangement without following a competitive bidding process, Newzshewz has learnt on good authority.
However, the minutes of the Authority’s decision have reportedly not yet been signed by all concerned members and senior officials for reasons best known to them, the sources added.
According to the sources, the Authority has rejected the company’s request for further extension in coal procurement without transparent bidding, maintaining that any discount secured by other power plants should also be available to PQEPCL.
The Authority is also expected to consider and approve the coal procurement bids submitted by the company, with preference likely to be given to suppliers offering the maximum discount against the relevant international coal price indices.
During a public hearing on November 26, 2026, Director General (Tariff) Muhammad Yousaf confirmed that the issue of coal procurement by PQEPCL was under consideration by the Authority and that its decision would be communicated soon.
Insiders claim that the company’s Chief Executive Officer (CEO) has held official meetings with NEPRA members to seek an extension in coal procurement without competitive bidding after submitting a formal application to the regulator.
There are also reports of informal meetings between company representatives and certain other stakeholders to explore an “amicable” solution to the issue.
The Korangi Association of Trade and Industry (KATI), in a letter to NEPRA, has also urged the regulator not to grant any further extension to PQEPCL for coal procurement under an interim arrangement without competitive bidding, warning that electricity consumers could be exposed to millions of dollars in avoidable fuel costs.
According to KATI, NEPRA had directed fresh competitive procurement of coal for PQEPCL through its decisions issued in October 2025. Subsequently, an order dated June 18, 2026, allowed the company a further interim period of three months, which expired on September 18, 2026.
The association maintained that another extension would prolong procurement on potentially less competitive terms and deprive consumers of the benefits of transparent bidding.
KATI claimed that other power plants had reportedly secured discounts of $7.12 per metric tonne and $5.66 per metric tonne against the API-4 index, while a discount of $5.66 per tonne was also reportedly available in PQEPCL’s current tender.
However, coal supplies to PQEPCL were reportedly being priced at a discount of only $1.08 per tonne, which was reflected in its fuel cost calculations.
The association estimated that the difference of $6.04 per tonne between the discount of $7.12 and the existing discount of $1.08, applied to approximately three million tonnes of coal, represented a potential avoidable cost of $18.12 million.
The controversy also involves competing procurement offers, including bids offering a discount of $2.10 per metric tonne for South African-origin coal. According to information available, this discount has been described as the highest obtained by PQEPCL in its procurement history.
Under the coal supply terms contained in the procurement documents, bidders are required to sell and deliver coal according to the agreed delivery schedule. The purchaser is required to notify the bidder in writing of the aggregate quantity required at least 45 days before the expected discharge of the shipment.
The pricing mechanism varies according to the country of origin of the coal.
For South African-origin coal, settlement is linked to the monthly average of the FOB Richards Bay index, expressed in US dollars per metric tonne on a 6,000 kcal/kg net-as-received basis and published by Argus/McCloskey as the API4 Index for the month in which the relevant bill of lading is dated.
For Indonesian-origin coal, the settlement price is linked to the monthly average FOB Indonesia Coal Index on a 4,600 kcal/kg net-as-received basis, published by Argus/Coalindo as the ICI3 Index for the month corresponding to the bill of lading date.
The competing procurement positions have raised questions about the commercial terms available to PQEPCL, the treatment of bids received under the ongoing procurement process and the justification for continuing with existing suppliers instead of securing more competitive offers.