ISLAMABAD: AsiaPak Investments Limited has approached the National Grid Company of Pakistan (NGC) and Independent System and Market Operator (ISMO) for initiating a comprehensive grid connectivity assessment for its proposed 1.5 million tonnes per annum aluminium smelter in the Port Qasim-Dha beji industrial corridor of Sindh, a project that is expected to require up to 2,357.4 megawatts (MW) of electricity at full development capacity.
The proposed export-oriented primary aluminium smelter, which is planned to commence commercial operations with an initial production capacity of 500,000 tonnes in the first quarter of 2029, is envisaged to be expanded to one million tonnes by the first quarter of 2033 and 1.5 million tonnes by the first quarter of 2035.
In this regard, Shaheryar Chishty, Chairman of AsiaPak Investments Limited, has formally approached the chief executives of NGC and ISMO through a letter dated November 25, 2026, seeking technical guidance on the availability of electricity from the nearby transmission network, identification of an appropriate point of connection, assessment of available network capacity and the process for securing necessary technical approvals.
The company has requested both entities to initiate the study inception process and identify the technical requirements, transmission infrastructure and system reinforcement measures necessary to accommodate the substantial electricity demand of the proposed industrial facility.
According to preliminary engineering estimates shared with NGC and ISMO, the project’s peak active electricity demand will increase progressively from 785.8 MW in the first phase to 1,571.6 MW in the second phase and 2,357.4 MW in the third phase.
The corresponding annual electricity requirements have been estimated at 6.598 million megawatt-hours (MWh), 13.196 million MWh and 19.794 million MWh, respectively, representing the energy requirement at full-production operation at each development stage.
The proposed development programme and electricity requirements are as follows:
| Development phase | Target commercial operation | Annual production capacity | Peak electricity demand | Annual energy |
| Phase I | Q1 2029 | 500,000 tonnes | 785.8 MW | 6.598 million MWh |
| Phase II | Q1 2033 | 1 million tonnes | 1,571.6 MW | 13.196 million MWh |
| Phase III | Q1 2035 | 1.5 million tonnes | 2,357.4 MW | 19.794 million MWh |
The company has clarified that the figures for the first phase are based on preliminary engineering estimates, while those for the subsequent phases are proportional planning estimates that would be refined as the project design develops.
It has also explained that annual energy figures represent full-production operations and should not be treated as forecasts of electricity consumption during commissioning or the initial production ramp-up.
Continuous electricity supply and progressive load build-up
An important technical consideration highlighted by the company is the nature of the aluminium smelting process, which requires continuous operation and a substantially steady electricity load once the potlines are commissioned.
According to the letter, the entire electricity demand will not materialise in one step. Instead, the load will build progressively during commissioning as different components of the smelting facility become operational.
AsiaPak has informed NGC and ISMO that construction demand, initial energisation, potline start-up, reactive-power requirements and the detailed monthly load build-up will be provided in coordination with its technology partner, GAMI.
The company has specifically requested that the initial grid study establish an agreed design demand, incorporating appropriate allowances and sensitivity cases to account for different operating conditions and the progressive expansion of the facility.
This aspect is considered important for determining the actual transmission capacity required at different stages, rather than designing the grid connection exclusively around the ultimate peak demand of 2,357.4 MW.
Proposes new 500/220 kV smelter substation
Regarding the proposed grid connection, AsiaPak has requested NGC to assess electricity supply from the nearest technically suitable transmission substation or transmission circuit serving the project area, with adequate provision for subsequent expansion.
One of the options proposed for examination is the construction of a new 500/220 kV smelter substation, connected through a single-circuit loop-in/loop-out arrangement on the KKI-PQEPCL connection.
However, the company has made it clear that this is only an option for technical assessment and has sought NGC’s recommendation regarding an alternative arrangement if it offers better security of supply, electricity deliverability, implementation time or overall cost.
The proposed arrangement would require confirmation of the existing transmission circuit configuration, availability and suitability of the route and the precise location of the proposed industrial facility, which the company has identified as either KIP or DSEZ.
The establishment of a dedicated 500/220 kV substation would be an important component of the proposed connection infrastructure. However, the final configuration would depend on the findings of the network studies and technical recommendations of NGC and ISMO.
The company has also requested that the proposed connection arrangement should accommodate subsequent increases in electricity demand as the smelter’s production capacity expands from 500,000 tonnes to 1.5 million tonnes annually.
PQEPCL proposed as commercial source of electricity
Another significant aspect of the proposed project is the company’s plan to develop a commercial arrangement for capacity and electricity supply from Port Qasim Electric Power Company Limited (PQEPCL).
AsiaPak has informed NGC and ISMO that it is simultaneously developing the proposed commercial arrangement with PQEPCL and has requested that the grid studies take into account both normal electricity supply conditions and circumstances involving reduced generation from the power plant.
The company has specifically identified generating-unit outages and transmission contingencies as situations that should be incorporated into the technical assessment.
It has also emphasised that the commercial source of electricity should not be treated as restricting physical power flows in the interconnected transmission network.
In other words, the company wants the grid assessment to examine the actual technical requirements of delivering electricity to the smelter under different operating scenarios, rather than limiting the assessment to the proposed commercial supply arrangement with PQEPCL.
This would require NGC and ISMO to evaluate the availability and reliability of the relevant transmission infrastructure under normal as well as contingency conditions.
The letter, however, does not indicate that a final power purchase agreement or an approved grid connection arrangement has been concluded with PQEPCL or NGC.
Comprehensive grid studies sought
AsiaPak has requested detailed guidance from NGC and ISMO on the scope, methodology, data requirements and approval process for conducting the necessary grid studies.
The proposed studies would cover six major technical areas.
First, the company has sought a comprehensive network load-flow and capacity assessment for each development phase, including N-1 contingency analysis and relevant seasonal generation and demand conditions.
This assessment would help establish whether the existing transmission network can accommodate the proposed electricity demand and what additional infrastructure might be required to ensure reliable supply.
Second, the studies would examine short-circuit levels, equipment ratings, protection coordination and the proposed substation and busbar arrangements to establish the technical suitability of the connection.
Third, AsiaPak has sought dynamic and transient stability assessments, covering generation loss, transmission circuit outages, voltage and frequency disturbances and the sudden rejection of the smelter load.
The company has specifically highlighted sudden rejection of the substantial industrial load as a scenario requiring examination, given the potential implications for the operation and stability of the interconnected power system.
Fourth, the studies would examine reactive-power compensation, voltage control, harmonics and power-quality performance of the rectifier installations associated with the aluminium smelting process.
Fifth, the company has sought technical recommendations concerning commissioning and energisation arrangements, progressive load ramp-up, operating restrictions and any remedial-action schemes required for secure operation.
Sixth, the assessment would cover transmission reinforcement, metering, telecommunications, supervisory control and data acquisition (SCADA), operational interfaces and the allocation of responsibilities at the grid connection boundary.
The company has also requested confirmation of the network and load models required for the studies, the procedure for appointing an acceptable study consultant and access to relevant system data.
In addition, it wants NGC and ISMO to clarify the sequence of technical reviews and the indicative time required for completing the studies and securing connection approvals.
System restoration and emergency supply arrangements
Apart from normal grid connectivity, AsiaPak has also sought guidance on system-restoration and emergency-supply requirements that should be incorporated into the project’s connection and operating arrangements.
Given the proposed continuous-operation nature of the aluminium smelting process, the company wants these aspects to be addressed during the initial planning and study phase.
The company has requested that NGC and ISMO identify the technical and operational arrangements necessary to address emergency conditions and system restoration.
These requirements are also expected to be considered alongside the proposed commissioning programme, energisation arrangements and progressive increase in electricity demand.
Seeks initial meeting within two weeks
Highlighting the urgency of the matter, AsiaPak has informed NGC and ISMO that the first phase of the project is targeted to achieve commercial operation in the first quarter of 2029 and that confirmation of the grid connection arrangement is a critical dependency for engineering, financing, procurement of long-lead electrical equipment and construction.
The company has stated that grid energisation would be required ahead of commercial operations to facilitate support testing and progressive commissioning, with the required date to be agreed through a joint programme.
It has therefore requested NGC and ISMO to nominate technical focal persons and arrange an initial joint meeting within two weeks of receipt of the letter, if practicable.
The proposed meeting would be used to agree on the terms of reference for the grid studies, information requirements, allocation of responsibilities and a time-bound programme for study completion, technical reviews and connection approval.
AsiaPak has also requested early identification of any network constraints, transmission reinforcement requirements or approval-related dependencies that could affect the project implementation schedule.
The company has indicated that its team would coordinate with GAMI, its technology partner, and relevant transmission stakeholders to provide the technical and project information required for the assessment.
The letter has also been copied to the Federal Minister for Energy (Power Division), Secretary Power Division, Director General Special Investment Facilitation Council (SIFC) and Secretary Ministry of Industries and Production for information and facilitation.
Major challenge for transmission planning
The proposed aluminium smelter represents a substantial prospective industrial electricity demand that would require coordinated planning by NGC and ISMO, particularly as the project envisages a progressive increase in consumption over three development phases.
The ultimate peak demand of 2,357.4 MW and annual electricity requirement of approximately 19.8 million MWh would make the availability of transmission capacity, reliability of supply and system stability important considerations in determining the feasibility and timing of the proposed connection.
The first phase alone is expected to require 785.8 MW, with demand subsequently doubling to 1,571.6 MW and reaching 2,357.4 MW following the third phase.
Consequently, the grid connection assessment would need to take into account not only the initial requirements but also the infrastructure and system capacity needed to accommodate the subsequent expansion without requiring disruptive changes to the connection arrangement.
For NGC and ISMO, the immediate task would be to establish the technical feasibility of the proposed connection, identify the most suitable transmission infrastructure and determine whether additional network reinforcement would be necessary.